Client |
Forestry Commission |
|
Architect |
Acanthus Holden |
|
Main Contractor |
|
|
Type of Development |
Visitor centre within the Cambrian mountains, near Aberystwth |
|
Reason for Green Roof |
Planning requirement as the structure was in a forestry area and was required to blend into the background |
|
Type of Roof |
Index INSTA Extensive Green Roofing System |
|
Size of Green Roof |
350m2 |
|
Build up of Roof |
Waterproofing |
|
Comments |
A successful installation of two pitched roofs with slopes of up to 26% installed in atrocious weather conditons |
|
Completion Date |
June 2002 |