Client |
Whitbread |
|
Architect |
ADS Design |
|
Main Contractor |
Pearce Construction |
|
Alumasc Approved Specialist Sub-Contractor |
Douglas Roofing |
|
Type of Development |
(Commercial) Pub and Restaurant |
|
Reason for Green Roof |
A Green roof was specified as it provided an environmentally friendly solution and is part of a major £21 million Torquay waterfront regeneration, designed to revitalise the waterfront and harbour area. |
|
Type of Roof |
Alumasc ZinCo Extensive Green Roof |
|
Size of Green Roof |
1000m2 |
|
Build up of Roof |
The extensive green roof was installed on a sloping roof, the build green roof system build up comprised the following: |
|
Comments |
|
|
Completion Date |
July 2004 |